Blunts Bar 2003
Managed Reserve

Dates Planted
5/23/03 -- 14.6 m, 5/30/03 -- 8.9 m, 9/24/03 -- 6.5m,
10/03/03 -- 5.9 m

Total UMCES
35.9 million of various broods

Acreage
24 acres

Site Preparation
• 31 acres were bar cleaned from 5/14-5/23
• ACOE planted 4.581 cubic yards mixed shell over
  10 acres on 7/16
• DNR planted 5.776 cubic yards of whole shell and   fines over 14 acres
• April 16 Acoustic survey conducted by MGS/DNR
  completed. Click here for results.

Project Supporters
UMCES, MWA, DNR, NOAA, ACOE, MES

Disease Data (UMCES Paynter Labs)